Workplace in the Task Force

Does anyone know how an obstacle in the taskbar can occur? I am using TFS 2013. The process template is for Scrum. I tried to put this work item in the task category, but it does not work.

+6
source share
1 answer

You must change the states in Impediment.xml to the same states as in the Task work item, you also need to redo the transitions to copy the states and transitions from Task.xml to Impediment.xml

<STATES> <STATE value="To Do" /> <STATE value="In Progress" /> <STATE value="Done" /> </STATES> 

Aditional you must add this type of work item to TaskCategory in Categories.xml

 <CATEGORY refname="Microsoft.TaskCategory" name="Task Category"> <DEFAULTWORKITEMTYPE name="Task" /> <WORKITEMTYPE name="Impediment" /> </CATEGORY> 

What all.